How to Add POETAF to a Posted Payables Transaction


Overview


This article provides explanation of how to add the POETAF information to reclassify a Payables transaction to make it visible on a Project in PPM sub-ledger (If POETAF wasn't provided on the initial payables invoice). When a cost needs to be visible on a Project in PPM, you must include the POETAF on any Requisition/PO, Non-PO Payment Request, Concur transaction, etc. This article also discusses how to update POETAF information including Expenditure Type and Expenditure Item Date

Essential Information


Next Steps


1. Access the GL-PPM reconciliation report.

2. Follow the instructions on the blink page to identify GL to PPM discrepancies.

3. Using data retrieved from the report, download and complete the Cost Data Transfer Request Excel Spreadsheet, using these guidelines:

  1. Amounts should be the aggregate amount, not individual lines for each item on the invoice/transaction.
  2. Expenditure Type should be the full number and name combination as shown in the example, e.g. 534100 – Computer Supplies under $5K, and the number should match the Account Code.
  3. Funding Source should be populated with the number.
  4. You may also include data for the following two issues on the same attached spreadsheet, i.e. collective of many Payables transactions at once:

4. Fill out the Subledger Transaction Correction Form through Services & Support.

 

You can also update the Expenditure Type or Expenditure Item Date on Posted Payables Transactions that did post to PPM by following these steps:

  1.  Complete the Cost Data Transfer Request Excel Spreadsheet.
  2. In the Transfer To fields of the file, enter where you would like the charge moved to.
    1. If you're updating the Expenditure Type, be sure to also update the Account Code accordingly. All other fields should match the information in the Transfer From section.
  3. Fill out the Subledger Transaction Correction Form through Services & Support.

 

Tips to Avoid GL-PPM Variances


If you intend to have expenses hit PPM, include FULL POETAF details (especially Project, Expenditure Type, Task, and (if applicable) Funding Source).

Questions?


Need assistance with a cost transfer? Refer to this guide to determine the appropriate next steps.

If you need any additional assistance, please submit a ticket here.