Overview
This article teaches how to add a line to an existing Purchase Order (PO), and also how to decipher when to complete this process in lieu of issuing a new Purchase Order.
Essential Information
- Please note, using this feature will lock out all future Requestor Initiated Change Order functionality.
- If the PO has Closed or Finally Closed status you cannot add a line to the PO.
- You may add a line to an existing PO when one or more of the following applies:
- Adding next year of funding on a multiyear, federally-funded PO.
- The justification field should note a continuation of service for year XYZ.
- Changing the COA or POETAF information on the PO.
- Should be used to address AP Invoice Holds and to address errors on the COA/POETAF.
- The justification field should note a simultaneous reduction of the original PO to what has been invoiced.
- Missing charge on the original PO to close PO.
- The justification field should note the original charge missed on the order such as Shipping, Installation, Miscellaneous Fee
- Typically Shipping should not be added as a line item. For more information please see How to Reference Shipping Charges on a Requisition
- The incorrect form was used on the original PO.
- Refer to KB0032726: Overview of Request Forms in Oracle Procurement to review of when the amount-based versus the quantity-based form should be used.
- For Add A Line to Existing PO Change Orders that do not fit one of the above criteria, the request will be denied.
- If a new or revised Statement of Work (SOW) needs to be attached, please issue a new PO.
Next Steps
Navigate to Oracle Procurement
- Go here
- Click the Company Single Sign-On button.
- Log in with your Active Directory information.
- In Procure to Pay, click Purchase Requisitions.
Select a Form
- In the forms section, click one of the Add line to existing PO links.
- If you are unsure which one to select, refer to KB0032726: Overview of Request Forms in Oracle Procurement for a review of when the amount-based versus the quantity-based form should be used.
Complete and Submit the Form
- Review the instructions at the top of the form and within the Attachments section for relevant tips and required attachments.
- All fields with an asterisk are required.
- If you have any trouble completing the request form, please refer to KB0034364: How to Order Goods and Services with Request Forms in Oracle Procurement.
- In the Justification field, include the reason why you are requesting a new line be added to the Purchase Order.
- Federal Funds: Please add year XYZ of the Federal Funds based on the new Notice of Award attached.
- AP Invoice Holds/POETAF Issue: Please add a new line with the updated COA/POETAF and reduce the line XYZ to the invoiced amount.
- Missing Charge: Please add a new line to pay for missing charge XYZ to close the PO.
- Incorrect Form: Please add a new line to correct the PO using an Amount-Based line instead of a Quantity-Based PO.
- Once completed, at the top right of the page, click Add to Cart.
- At the top right, click the Shopping Cart icon, then Review to begin the submission process.
- For guidance on the Checkout process, please refer to KB0032058: How to Checkout in Oracle Procurement.