Cost Transfer Guide


Overview


Critical Concepts


Steps to Take


Decision Matrix

Transactions Originated/Created in OFC

 Cost Transfer Type

Self-Service

Services & Support

  • Project to Project 
Department can process in OFC using PPM Cost Transfer functionality
Home > Projects and Awards > Costs > Manage Project Costs
N/A
  • For a Posted Payables Transaction:
  • Non Project to PPM Project (i.e. the Project Number in the chart string was 0000000 and no POETAF was provided)
    • Department Error: Project Number and POETAF was not entered on the PO/Non-PO Payment Request/Concur/Etc.
    • System Error: Freight/Miscellaneous/Tax Line did not post to the COA + POETAF, though the other lines on the transaction did
  • GL Project Segment only to PPM Project (i.e. chart string with Project Number other than 0000000 but no POETAF provided)
  • Project to Non Project (i.e. chart string included Project Number other than 0000000 and POETAF, but shouldn’t have)
N/A

Download and complete the Accounts Payable Cost Data Transfer Request Excel and submit via Non Salary Cost Transfer Request through Services & Support

  • GL Project Segment only to PPM Project (i.e. chart string with Project Number other than 0000000 but not in PPM)

Note, this is only for expenses/costs. Resources/revenue are only in the GL

Ex. Not a requirement, but for example, may be used to move payroll expenses to a Project
General Project to Project 0000000 (Non Project)  Non Project - NON RECHARGE

N/A

Contact originator of journal/GL entry

If from Accounts Receivable, contact contact originator:
About: Billing & Receivables
Related to: Oracle Accounts Receivable
More Specifically: AR Billing Other

If from Internal Controls & Accounting, contact originator:
About: Financial Accounting
Related to: General Accounting Support
More Specifically: Other General Accounting Inquiry

If from MedCenter, contact
Michelle York myork@ucsd.edu
  • Graduate Student Stipend, Fee Payment and Tuition Remission
Requests for funding or other retroactive changes must be submitted via the FSRT.

Cost transfers may be processed by the Financial Support Unit for international students as needed.

Generally Unallowable Transfers - Same Project but Changing Expenditure Type or Expenditure Item Date  

 Cost Transfer Type

Self-Service

Services & Support

  • Change in in Expenditure Type on AP Transactions created in OFC for a Sponsored Project or General Project
  • Change in in Expenditure Item Date on AP created in OFC Transactions for a Sponsored Project or General Project
N/ADownload and complete the Accounts Payable Cost Data Transfer Request Excel and submit via Non Salary Cost Transfer Request through Services & Support
  • Change in Expenditure Type on Recharge Transactions for a Sponsored Project
  • Change in Expenditure Item Date on Recharge Transactions for a Sponsored Project
 Contact the Recharge Unit/Department that charged the project
  • IFIS Conversion Expenditure Item and Type Change for Sponsored Project Only
N/AContact the appropriate Award Accountant to process your request
  • Indirect Cost (IDC)/Burden

N/A

Contact the appropriate Award Accountant to process your request

IFIS Conversion (Payroll and Non Payroll)

Cost Transfer Type

 Self-Service

 Services & Support

  • Sponsored Project to Sponsored Project
  • Sponsored Project to General Project

Department can process in OFC using PPM Cost Transfer functionality

Home > Projects and Awards > Costs > Manage Project Costs

N/A
  • General Project to Sponsored Project
  • Project 0000000 (Non Project) to Sponsored Project
Note that these are manual and will have the actual expenditure type and from/to

N/A

Submit a Non Salary Cost Transfer Request or a Salary Cost Transfer Request

If you still have questions or need additional assistance, please submit a ticket