Overview
This article teaches how to change the start or end date referenced on a purchase order. You can do this by initiating a change order, and updating the period of performance.
Essential Information
- Only the individual who submitted the requisition may process the change order.
- The period of performance on a purchase order is not required to be edited after the fact, as the PO will not close once the end date has been reached.
- It is more important to make sure quantity-based POs have sufficient quantities, and amount-based POs have sufficient amounts.
- If the PO has additional funds after the PO end date has been reached, the PO does not need to be closed.
- You only need to update the period of performance at the supplier's request or for your own department's records.
Next Steps
Initiate a Change Order
- In Oracle, click Procure to Pay then Purchase Requisitions.
- At the top of the Oracle Procurement homepage, click Manage Requisitions.
- In Manage Requisitions, search for and select the requisition.
- On the requisition, click Actions then Edit Order.
Update the Period of Performance
- Above the lines, click the pencil.
- In Edit Line, scroll down to Notes and Attachments.
- In Note to Supplier, enter a comment with the format "Updated Period of Performance: MM/DD/YYYY - MM/DD/YYYY"
- Click OK
- In Description, indicate the period of performance has been updated.
- Click Submit